Why I Told Management the Plan Would Not Hold
At Bupa Aged Care, management set a fixed timeline and budget before anyone on the engineering team had provided estimates. The project involved replacing an ageing legacy CMS for Bupa Australia's customer-facing website, which was severely limiting information, responsiveness and user experience. The goal was to migrate Bupa UK's aged care website into a bespoke, responsive portal for Australian customers. However, management established the target schedule upfront, fixing the timeline duration of 3 months. Facing a deadline set without technical input, I knew as the Scrum Master that I had to tell management the plan would not hold. The Decision I guided a Scrum team through the migration effort while coaching stakeholders in Agile principles and removing delivery barriers. Rather than relying on subjective opinions or pushing back without evidence, I anchored our delivery strategy directly in performance data. I tracked the team velocity from day one of the project and us...