Context switching is a symptom: what unset expectations cost a delivery team
At Service NSW, my squads typically serviced five or six projects and clients at once, across licensing, revenue, health and education. Each agency had its own deadline, and each treated its request as the urgent one. Switching between them was only half the problem. When we were ready to engage an agency and asked for what we needed to configure their requirements, such as callback URLs and privacy URLs, they often did not have them. Waits ranged from two weeks to six months, and some engagements were cancelled midway. In my experience, the agency had usually realised it was solving the wrong problem, or lacked the funding or people to support the work. We could not park that work cleanly. We moved to the next agency, and when the first came back, we had to reload the context. The cost The costs were mostly intangible but real: lost focus, demotivation and low morale, all feeding into delays. On the coordination side, we averaged 2.7 hours per incident, with delays of one to ...